At the moment I am finished with the bottom plank, stringers are installed, most of the frames are ready to be installed and the centre board casing is about half done.
I started the build on Nov 19th and stopped for Christmas on Dec 20, during that time I spent about 59h on the build. This corresponds to an average of almost 2h/day or 13h/week.
So if I continue in the current pace and my initial assumptions concerning build time is correct it will take me 30 weeks to complete the boat, which means launching will be end of June.
I better increase the pace a bit.....