Wednesday, December 28, 2011

Time accounting

No picture today only some time analysis. When starting the build I assumed I would spend around 400h before launching.

At the moment I am finished with the bottom plank, stringers are installed, most of the frames are ready to be installed and the centre board casing is about half done.

I started the build on Nov 19th and stopped for Christmas on Dec 20, during that time I spent about 59h on the build. This corresponds to an average of almost 2h/day or 13h/week.

So if I continue in the current pace and my initial assumptions concerning build time is correct it will take me 30 weeks to complete the boat, which means launching will be end of June.

I better increase the pace a bit.....

2 comments:

  1. I go through the same logic but alas life gets in the way - http://bursledonblog.blogspot.com/2010/12/motivation.html

    Good luck with the build look forward to seeing the launch - meantime I'm going to step up work on the SCOW!!

    Max

    ReplyDelete
  2. Indeed, life is what happens while you are busy making other plans, right....

    ReplyDelete